"So, why don't you stipulate that it's going to be practically a 24/7 operation," Manalapan Planning Board member John Castronovo asked a developer's attorney in October, according to the Asbury Park Press. The board was considering a 232,920-square-foot building across Route 33 from Monmouth Battlefield State Park. It voted unanimously to deny it, and the room cheered.
That vote is one of three. Three parcels along the corridor got different decisions in 2026: a state purchase, a denial and an approval.
Three Parcels, Three Kinds of Answer
| Parcel | What was proposed | 2026 outcome | Further context |
|---|---|---|---|
| Former strawberry farm, Highway 33, across from the park's main entrance | 48,000 sq ft of industrial space | Bought by NJDEP Green Acres for $15 million, now part of the state park | Now state parkland |
| 51 Highway 33, Block 79.02 | 232,920 sq ft flex building, 218,965 sq ft of it warehouse | Denied by the Planning Board in October | A developer that already won a zoning ruling in court |
| Route 33 and Woodward Road, Blocks 73 to 75 | 502,031 sq ft warehouse plus a 40,150 sq ft recreation center | Amended plan approved 7 to 2 in June | NJDOT approval and a pending challenge to the redevelopment plan |
A purchase closed the first row. The second turned on conditions the board asked for, and the third is an approval that still depends on a state agency and a court.
The Farm the State Bought
On August 5, 2026, the New Jersey Department of Environmental Protection announced that its Green Acres Program had bought a 22-acre property along Highway 33 in Manalapan from Monmouth Battlefield Flex, LLC for $15 million. The money came from Green Acres State Land Acquisition funding and the federal Land and Water Conservation Fund, and the Monmouth Conservation Foundation helped with early talks with the owner.
The land sits directly across Route 33 from the park's main entrance. It already had approval for 48,000 square feet of industrial space, according to the Press of Atlantic City. That approval, granted at a March 2024 planning board meeting, required a Phase 1A survey to check for Revolutionary War artifacts. The DEP says surveys and historical considerations indicate troops may have used or crossed the property during the 1778 battle.
The farm is now an addition to Monmouth Battlefield State Park, which covers 2,764 acres with it included. New Jersey State Parks will manage its open fields and wooded trails for future public recreation, interpretation, education and research. Friends of Monmouth Battlefield President Dr. David Martin said in the release that the purchase "will help preserve for posterity the viewshed and environs of the park."
The state bought the land after an industrial project had been approved.
The October Denial
The parcel next door at 51 Highway 33 was decided by a vote, and the reasons for that vote matter more than the vote count.
The developer, 51 Route 33, LLC, formerly Mercer Realty Partners, LLC, first came before the board in 2022. The site's zone allows flex space but does not allow a standalone warehouse. Board members asked whether a building that was mostly warehouse, with a few small units for other uses, really counted as flex. In April 2022, board member Jack McNaboe described the flex operations already in town as tradespeople such as plumbers and electricians "taking up 10% of the building, 20% of the building," the Asbury Park Press reported.
The developer sued the township's land use boards in April 2023. On March 31, 2026, Civil Presiding Judge Owen C. McCarthy ruled for the developer, writing that "The Original Flex Space Ordinance (Ordinance 2012-11) is unambiguous." After the ruling, the developer came back with plans that cut the warehouse portion by 0.7%. The October plan had 218,965 square feet of warehouse, three units of 2,675 square feet each for contractor shops, assembly and wholesale trade, 4,400 square feet of office and a 1,530-square-foot common corridor.
When the board voted in October, its stated objections, according to the Press, were the developer's refusal to commit to operating hours, a left-turn lane, and a limit on how many weeks trailers could be stored on site. The developer had proposed two warehouse shifts covering roughly 7 a.m. to 11 p.m. on weekdays and Saturday hours of "morning to 5 p.m.," but said it would not commit to them. Its attorney, Ron Shimanowitz, gave the developer's view:
"There's no township ordinance or code that limits the hours of operation. The board wanted to know an idea or concept of what the hours are, this is what we contemplate they will be. But to ask the applicant to commit as a condition to those hours is unfair because it's not required."
He also argued that the left-turn lane falls under the state Department of Transportation and that local law sets no limit on trailer storage. Board members responded that they can still make those requests.
The archaeology also did not support a denial. The developer's archaeologist, Jacob Spuck, reported 126 shovel tests and 23 surface artifacts from the late 1800s and early 1900s. He described them as domestic items unrelated to the 1778 battle, and the township's archaeologist agreed that more digging was not warranted.
So the court had already sided with the developer on the flex-space question, and the denial rests on conditions the developer says the code does not require. That makes it a different kind of outcome from the farm next door. A buyer looking at homes nearby, including the Village Grande community that the Press names as a neighbor of the site, should keep this parcel on the list of open questions.
The Warehouse That Already Has Approval
Farther along the corridor, at Route 33 and Woodward Road, the larger project is already approved.
AAGWML-F Property, LLC's warehouse received preliminary approval in 2024. In 2026 the developer returned with an amended plan. It reduced the warehouse from 575,596 to 502,031 square feet and replaced a 55,003-square-foot recreation center with two ice sheets with a 40,150-square-foot building with one sheet, lowered about 3.5 feet to a height of 34 feet. The revision with the most effect on daily traffic moved the jughandle from an off-site connection at Sawgrass Drive onto the project's own property, lined up with the entrance road to the Manalapan Landing community.
The Planning Board approved the amended site plan and major subdivision on June 25, 2026, by a 7 to 2 vote, with members Kastell and Nelson voting no. The June 25 minutes are posted on the township site. The board memorialized the resolution on August 13, with a condition that NJDOT approve the plan before construction begins.
This project has open dependencies of its own. At the June 11 hearing, an attorney for Gaitway Farms told the board that litigation against the township and Planning Board over the redevelopment-plan amendment was still pending. That amendment is Ordinance 2026-01, which the Township Committee adopted after the Planning Board reviewed it for consistency with the Master Plan. The applicant chose to move ahead knowing the approval could later be overturned.
Reading a Route 33 Listing With This in Mind
These three parcels show why nearby land and development plans may matter to a buyer. A wooded lot on an aerial photo tells you nothing about its status, and a cheering hearing room does not mean a project is gone. Here are some ways to learn more:
- Confirm whether nearby open land is publicly owned. The former strawberry farm is now state parkland. Private land that happens to be undeveloped is a different case.
- Read the minutes, not just the headlines. Manalapan posts Planning Board agendas, minutes and some full transcripts at mtnj.org. The June 11 transcript alone covers the jughandle placement, building heights and pending litigation.
- Map the traffic changes, not only the buildings. The approved jughandle lines up with the Manalapan Landing entrance. The board also asked for a left-turn lane for the denied project. Road changes like these affect daily driving more than building square footage does.
- Watch the agendas after you close. Both the denied and the approved projects can still come back before the board or go to court.
This post covers land-use decisions as reported and is general information, not legal advice. For questions about a specific property's zoning or any pending litigation, consult a land use attorney.
Next Door in Millstone
Millstone Township, which shares the Route 33 corridor, is moving in the same direction. In October 2026, a planner presented a Millstone master-plan reexamination that proposes removing warehouses as a permitted use in the Planned Commercial Development zone and favoring smaller light-industrial and flex spaces, according to Citizen Portal. A hearing was scheduled for November 12. At the same time, Millstone's board extended the approvals for AACDML Property LLC's 130,242-square-foot Route 33 warehouse after the applicant cited inadequate electric service.
In Millstone, the proposal to curb large warehouses and the extension for an approved one came in the same month.
If you're considering a home anywhere along Route 33 in Manalapan, George Pavlushkin and The ELITE Group can discuss the addresses you're considering. Schedule a Free Consultation.